In 2023, a military aircraft incident occurred on the remote Melville Island off the northern coast of Australia. The incident and subsequent fire significantly damaged the pristine environment and contaminated the area with aviation fuel and composite materials, including carbon fibre, metals, fibreglass and thermoplastics.
Jacobs’ team in Darwin was uniquely positioned to assist and was rapidly engaged by the Commonwealth Department of Defence to provide project management and contract administration (PMCA), environmental investigation and remediation management services. With Jacobs’ support, the Department of Defence also engaged an experienced remediation contractor, Ventia, to deliver the remediation works. The project presented a range of factors that, while not unusual to encounter on their own, in combination resulted in a unique project environment. They included:
In particular, the impending monsoonal weather (October to April) created a challenging 13-week timeline to complete the investigation and remediation works. Any delay risked spreading contamination into waterways vital for hunting, fishing and drinking water on the Indigenous Mantiyupwi Country.
tons (965 tonnes) of contaminated soil and waste material removed from the pristine Melville Island environment
miles (2,681 kilometers) from the remediation site to the licensed waste management facility
miles (504,948 kilometers) travelled by soil samples for testing